| The Coal Store, Guilsborough | |
The
cob barn is a central feature in Guilsborough but it has been suffering
from a common earth building problem of water entering through the base
due to a raised ground level.The adjacent ground level land was lowered and the brickwork foundation walls were rebuilt and re-pointed |
|
Repairs
were then aimed at removing the decayed earth and replacing with pre-dried
clay blocks. The blocks were made using local clay that would match
the existing colour, texture and porosity. The building is not rendered
so a satisfactory surface finish was an important aspect of the work.
All mortar repairs were carried
out using a lime putty mortar. Another part of the project was to close
up holes that bees had burrowed into the walls; this was obviously
causing decay, albeit over a long period of time. This was carried
out without affecting the overall appearance or character of the structure.It is important that any substantial repairs are not “lost” within the building and for historical reasons there must be subtle differences between original material and any subsequent repairs. This will enable future generations to “read” the building. Internally one of the stores had further cob wall repairs carried out and the lime render was laid on top. The whole store then had three coats of lime wash applied. A
report of the work will be supplied to the Parish Council for their
records. This will enable future repairs to be carried out, with an
understanding of what has gone on before.(right: The Coal Store, after renovation) |

The
cob barn is a central feature in Guilsborough but it has been suffering
from a common earth building problem of water entering through the base
due to a raised ground level.
Repairs
were then aimed at removing the decayed earth and replacing with pre-dried
clay blocks. The blocks were made using local clay that would match
the existing colour, texture and porosity. The building is not rendered
so a satisfactory surface finish was an important aspect of the work.
All mortar repairs were
carried
out using a lime putty mortar. Another part of the project was to close
up holes that bees had burrowed into the walls; this was obviously
causing decay, albeit over a long period of time. This was carried
out without affecting the overall appearance or character of the structure.
A
report of the work will be supplied to the Parish Council for their
records. This will enable future repairs to be carried out, with an
understanding of what has gone on before.