Hopthorne Cottage Barby Northants

This cottage has suffered from structural movement over recent years. The end elevation shows the cracks and tell tales. The main contractor has taken the stonework down and installed a concrete foundation to help counter the movement problems.

Our involvement was to rebuild the solid stone walls, which are 22" thick! The walls are built to blend in with the existing remainder of the property. The bond of the existing stonework is a mix of random rubble and rough coursed, this arrangement is being matched using a 3.5 moderately hydraulic lime mortar

hopthorne
End elevation
hopthorne
The scaffold now in position prior to the stonework being taken down.
hopthorne
All the stonework on the end elevation and a small section on the front elevation has now been taken down.